Bamenda-Babadjou Road: New contractor takes over, tasked to deliver ASAP

The construction of the road linking Babadjou in the West Region to Bamenda in the Northwest has been awarded to a new contractor by the Minister of Public Works, Emmanuel Nganou Djoumessi. The announcement was made yesterday during a working session held at the Divisional Delegation of Public Works for the Bamboutos, in Mbouda, West Region. It was done in the presence of the Senior Divisional Officer for the Bamboutos, Franklin François Etapa.

The construction of Babadjou-Bamenda stretch of the road was launched in 2017 and has been experiencing several setbacks since then, ranging from the Anglophone crisis and lack of funds and material.

While the Babadjou-Bamenda stretch of the road continues experiencing these hurdles, the Yaoundé-Bafoussam-Babadjou section has been progressing well, while the Bamenda-Mamfe-Ekok stretch has been completed.

Taking to account the deficiencies of former contracted company, SOGEA SATOM, on the Babadjou-Matazem stretch, Minister Emmanuel Nganou Djoumessi of Public Works decided to mobilize a new contractor and a quality control firm for emergency works, under the supervision of the Regional Delegate for Public Works of the West.

Following heavy downpours after the meeting, the stakeholders surveyed road and examined the human and material resources necessary for the continuity of traffic in complete safety on this stretch of the road.

Mimi Mefo Info (MMI)

Recent Posts

31-year-old Woman Arrested After Aborting 8-month-old Baby and Dumping Body in Toilet at Nkwen

Dozens of people gathered at the residence of the woman believed to have aborted her…

10 hours ago

Please Don’t Take Drugs, They’re Satan’s Weapon to Destroy People — Brenda Biya Warns Youth

By Tata Mbunwe Brenda Biya has described drug abuse as the devil's weapon against people,…

12 hours ago

Impact-100 : vingt propositions et une question sans réponse claire, mouvement citoyen ou parti en gestation ?

L'interdiction de la conférence de lancement, ce samedi à Bonanjo, n'a pas empêché Impact-100 de…

2 days ago

Cameroon Remembers Rudolf Duala Manga Bell 112 Years After His Execution by Germans

Officials laying wreath at the grave of Rudolf Duala Manga Bell in Douala August 8,…

2 days ago

New World Vocational Training Institute: Menchum North MP to Support Registration of Trainees from Fungom, Furu-Awa Subdivisions

Hon Kum John Nji The Member of Parliament, MP, for the Menchum North Constituency, Hon…

3 days ago

Incarcéré après l’assassinat de sa maman alors qu’il avait porté plainte, Cabrel Zamboue est déclaré non coupable

Près de trois ans après avoir été arrêté dans l'enquête sur l'assassinat de sa mère,…

3 days ago